Our team have been out on the road, this time supporting a very busy hotel group in Liverpool
We were called out to inspect an old outdated booster set.Â
Our engineers quickly identified that it had a faulty panel and was running on only one pump!
Our engineers shared a couple of possible solutions, with the client deciding to upgrade to a new unit, however, as the hotel was open 24/7 they could only have the booster set off for a minimal amount of time!
This is where the planning started…
- Agreed on the time for the minimal outage
- Our engineer decided a custom built booster set would best serve the hotel
- We isolated and removed the old set
- The new invertor driven energy saving set installed and the old outdated direct online unit removed
- The unit was commissioned and everything was good to go with the new set installed within the agreed timeframe!
An excellent job completed by the team, which now means this hotel will have no issues over what is an incredibly busy period.