The Challenge
When a faulty control panel began affecting the water supply at an NHS hospital, immediate action was required to avoid any disruption to patient care and essential services. With hospitals operating 24/7, timing was critical — meaning this job had to be completed out of hours with precision and planning.
Our Solution
Our engineers attended promptly, isolating the system at 4:30am to ensure no interruption to hospital operations. The entire control panel was replaced, tested, and recommissioned before staff and patients began their day — all completed safely, efficiently, and without incident.
The Result
The new control panel restored full operational control of the water system, ensuring reliability and compliance across the site. The hospital’s facilities team praised the speed, professionalism, and minimal disruption achieved during the out-of-hours works.
✅ Rapid out-of-hours response
✅ Complete control panel replacement
✅ Zero disruption to hospital operations
✅ Fully tested and recommissioned system
Trusted Support for Critical Environments
From hospitals to data centres and large commercial buildings, NT Cloke Pumps & Water provides specialist out-of-hours and emergency support to keep vital systems running.
Our engineers combine technical expertise with planning and precision — ensuring every client, no matter how complex their site, stays operational and compliant.
Contact our expert team for reliable support 24/7.
You may also like
Location: Midlands (Apartment Block)Service: Booster Set Upgrade & ReplacementSector: Residential / Apartment Building The Challenge NT Cloke Pumps & Water
Location: BirminghamService: Booster Pump ReplacementSector: Residential / Apartment Block The Challenge NT Cloke Pumps & Water were called to a
Location: UK (Severn Trent Project Site)Service: Booster Set Upgrade & ReplacementSector: Industrial / Water Infrastructure The Challenge NT Cloke Pumps
Location: Birmingham (School)Service: Heating Pump UpgradeSector: Education / School Facility The Challenge NT Cloke Pumps & Water were scheduled to
Location: UK (Office Block)Service: Heating Pump ReplacementSector: Commercial / Office Building The Challenge Our engineers were contacted after a heating
Location: LiverpoolService: Booster Set Upgrade & CAT 5 Water Tank InstallationSector: Residential / Apartment Block The Challenge Our engineers were
Location: UK (Commercial Site)Service: Bearing & Seal ReplacementSector: Commercial / Facilities Management The Challenge Our engineers were called to site
Location: Cardiff City CentreService: Non-Return Valve ReplacementSector: Hospitality / Commercial The Challenge Our engineers were called to a busy restaurant
The Challenge Our engineers were called to a student accommodation block in Birmingham following reports of a noisy pump within
Location: BirminghamService: Pump & Inverter ReplacementSector: Student Accommodation / Residential The Challenge Our engineers were called to a large student
Location: UK (Commercial Site)Service: Pump Inspection, Safe Removal & RepairSector: Commercial / Facilities Management The Challenge The client contacted us
The brief NT Cloke Pumps & Water were instructed to carry out a full tank clean and chlorination on Tanks