Booster Set Upgrade at a Care Home
We recently carried out a planned booster set upgrade at a care home, ensuring everything was completed within a tight timeframe to reduce disruption for residents and staff.
🛠️ Site Assessment & Preparation
Our team measured up during the initial visit and had a new booster system built to specification—ready for quick installation.
⏱️ Precise Execution
- Water supply turned off at 9:00am after breakfast
- New booster set installed
- Water fully restored before lunch at 12:00pm


The job was completed on time, with zero impact on daily care routines.
✅ End Result
A brand-new, efficient booster system now supports the property—installed with care, speed and minimal downtime.
You may also like
The Challenge NT Cloke Pumps & Water were called to a local school in Leicester following a fault on the
The Problem NT Cloke Pumps & Water were called to a major hotel in Birkenhead after a complete failure of
The Problem NT Cloke Pumps & Water were called to a school in Leicester following reports of a leak within
When a booster set inverter fails, maintaining a reliable water supply becomes a priority, particularly in environments such as schools
When a booster pump fails in a school environment, a fast and effective response is essential to maintain reliable water