NT Cloke Pumps & Water were contacted for an urgent weekend call-out after a site experienced a full controls failure caused by a power issue.

🔎 Diagnosis on Arrival
Our engineers arrived on-site Saturday morning to find:

  • Controls completely unresponsive
  • A blown inverter
  • A pump showing unbalanced resistance and clear signs of internal damage

⚙️ Our Response
We quickly got to work:

  • Replaced the faulty inverter
  • Electrically tested the existing pump
  • Supplied and installed a replacement pump from our own stock
  • Recommissioned the system and carried out full testing

Outcome
By Sunday, the system was back to full operation—ready for the client’s team to return Monday morning without disruption.